In a gesture aimed at benefiting the local community, the management of The Clarens Golf and Leisure Estate has agreed to return a borehole to the local Municipality. This decision follows an agreement made in December 2019, in which the estate was permitted to use a...
The goal is to retrieve and process 3 million liters of water per day. Currently, the existing plant can handle just 1 million liters daily, but the new facility will meet the increased demand once operational. Six new boreholes have been drilled, five of which are...
Construction at Serengeti Energy’s Boston Hydro project is progressing as planned, with attention shifting to preparations for the scheduled water outage of the Lesotho Highland Water Project from October 1 to March 31, 2025. This period will facilitate crucial...
In a meeting held on September 6, contractor Mr. Barnabas Mboweni of KLOK Engineering updated the Clarens Chamber of Commerce (CCC) on the ongoing development of six boreholes aimed at providing a sustainable water source for the town during the Lesotho Highlands...